ERP Implementation Case Study: From Excel and WhatsApp to One Integrated System
An export furniture manufacturer in Indonesia previously managed sales, purchasing and warehouse operations using dozens of Excel files, WhatsApp conversations and handwritten notes. Doodex helped bring these processes into one ERP system through a phased implementation, starting with the departments that were ready, without forcing the shop-floor team to abandon its established workflows.
Key Figures · April–October 2026
Data read directly from the client's system on 13 November 2026.
The Operational Challenges of an Export Manufacturer Before ERP Implementation
Each buyer has its own product codes, pricing and document formats. Before working with Doodex, most operations relied on separate files, manual communication and records maintained by individual staff members.
The factory ships approximately 10 containers per month, mainly to Europe, Australia and North America.
Proforma invoice preparation was time-consuming.
Admin staff had to gather information from multiple sources, including price lists, product catalogues for CBM calculations and technical drawings. A standard proforma invoice took 10–15 minutes to prepare, while a new product could take several days because the team had to wait for drawings from the drafter.
Purchasing data was scattered across different channels.
Purchase orders (POs) were managed through Excel, WhatsApp and email. Some orders were only sent through WhatsApp, leaving no centralised record.
Material consumption was recorded manually.
Foremen in each division recorded material usage by hand. As a result, stock levels and material movements also had to be tracked manually.
Operations depended on key individuals.
When the responsible admin was unavailable, work could come to a standstill. The business owner also had to step in to keep daily operations moving.
Sales, Purchasing and Warehouse Operations Now Run in One System
A phased ERP implementation helped the factory reduce administrative work, improve data traceability and give the business owner better visibility into daily operations.
Estimated time for one proforma invoice, down from 10–15 minutes.
Purchase orders recorded directly in the system since August.
Material transfers from warehouse to production since 8 September.
Sellable products in master data: pricing, CBM, collection and images.
Sellable products moved into more appropriate categories in one update.
85 sales orders from 21 buyers.
Proforma invoice preparation is significantly faster.
The estimated preparation time could decrease from 10–15 minutes to 1–3 minutes. Admin staff only need to enter the product code and quantity. Buyer-specific pricing, CBM, collection details and product images are automatically retrieved from a centralised master database containing 1,614 sellable products.
All purchasing activity is now recorded in one system.
Since August, the purchasing team has created purchase orders directly in the ERP system. Approximately 900 POs have been recorded, eliminating the previous reliance on WhatsApp conversations as the only record of some orders.
Material transfers to production are now documented.
Since 8 September, approximately 1,400 material transfers from the warehouse to production have been recorded by division and order. This replaces the handwritten records previously used to track material movements.
Export documents are generated without repeated data entry.
The SVLK logo, Certificate of Origin details, and container and seal numbers can be printed directly on sales orders and invoices. Admin staff no longer need to enter the same information repeatedly.
The business owner has better operational visibility.
A dashboard provides sales data by collection, identifies buyers who have not placed an order in the past year, and shows each customer's outstanding balance. These insights help the owner make more informed decisions, including reorganising product categories. In one update, 249 sellable products were moved into more appropriate categories.
Manufacturing Module: Current Progress
The manufacturing module is still under development. Historical data from 74 product costing files and approximately 3,300 cutting list files covering 2012–2026 has been imported into a test environment.
The import resulted in approximately 1,120 Bills of Materials (BoMs) and 25,800 cutting list lines. This data is currently being prepared for deployment to the production environment.
Building an ERP System Around Existing Shop-Floor Workflows
For Doodex, implementing an ERP system for a manufacturing company is about more than moving data into new software. The Odoo-based ERP system we build must fit the company's operational requirements and work for the people who use it every day. Want to know what else we do? See Doodex services.
Rollout order
- AprilSales & invoicing
- AugustPurchasing
- SeptemberWarehouse & production transfers
- In progressManufacturing
A phased rollout based on each department's readiness.
Doodex started with sales and invoicing in April, followed by purchasing in August, then warehouse operations and production transfers in September. The manufacturing module came later, once purchasing and inventory data had become more stable.
Preserving familiar workflows.
Order numbers continued to use buyer-specific codes, while document formats remained aligned with each buyer's requirements. Unnecessary menus were hidden so staff could focus on the features relevant to their daily work.
Hands-on support throughout daily operations.
Support did not end with the initial training sessions. The Doodex team provided daily assistance and demonstrations during weekly meetings. Within approximately six weeks, a salesperson who initially needed step-by-step guidance was able to make document corrections independently.
Migrating historical data with proper validation.
Thousands of Excel files were cleaned and mapped before being imported. When the first production data import resulted in unintended changes, the team rolled back those changes and repeated the import using stricter rules. The corrected import process was completed within three days.
What We Learned From This Project
One important lesson from this implementation was that project delays are not always caused by technical issues. In this project, many delays occurred while waiting for decisions or data from specific individuals.
For example, the goods receipt process could only be finalised three weeks later, once a warehouse lead had been appointed.
Based on this experience, Doodex places greater emphasis on three questions at the beginning of every module:
- Who is responsible for making decisions?
- Who owns and provides the required data?
- When must the decisions and data be ready?
“If we were to start this project again from scratch, I would make sure that every module had a clearly assigned decision-maker and data owner from the very first week, with defined deadlines, before any development work began.”
Frequently Asked Questions
The questions manufacturers ask us most before starting an ERP implementation.
Do all departments have to switch to the ERP system at the same time?
No. ERP implementation can be phased according to each department's priorities and readiness. In this project, implementation started with sales, followed by purchasing, warehouse operations and manufacturing. Each phase built on the previous one once the processes were running smoothly.
Can export documents still follow each buyer's required format?
Yes. The system can be configured to accommodate each buyer's document and information requirements. In this project, buyer-specific product codes, CBM, container and seal numbers, Certificate of Origin details and the SVLK logo can be automatically included in order and invoice documents.
What if our company data is still spread across multiple Excel files?
Historical data can be included in the ERP migration process. The Doodex team helps clean, map and import existing data into the new system. The imported data is then reviewed with your team before being used in daily operations.
Data Sources: Project team Q&A, 13 November 2026 (data read directly from the client's system with read-only access) · GRW Knowledge, 6 November 2026.
Ready to run your factory on one system?
Doodex supports manufacturers from process mapping to support after go-live. The rollout is phased, starting with the department that is most ready.
- 1ERP ImplementationSales, purchasing, warehouse and production in one system.
- 2Data MigrationData from Excel files is cleaned, mapped and imported safely.
- 3Training & CoachingShop-floor teams are coached directly until the system feels natural.
- 4Support After Go-LiveFixes and further development based on the factory's needs.